Pages

February 27, 2013

Drainage Repair


WHAT'S WRONG WITH THIS PICTURE?


Yep, that there is a low drainage catch basin, the result of a very successful fairway topdressing program. Over the years, so much sand has been applied to the fairways that now we are going through and raising things like sprinklers, valve boxes and now catch basins. On Monday the staff dug up and repaired all three of the low catch basins on the 4th fairway.


















Note the tree roots in the picture above and keep in mind that this drain is 30 yards from the nearest tree!



Once the drain is exposed, the old box is removed. A new connection is made at the 6" drain pipe and the hole is filled with a sand/soil mixture that will allow for the immediate area to drain better.


The area is then compacted and prepared for sod.


The finished result is a level area surrounding the catch basin. Not only do the catch basins look better but they will no longer be hard on our equipment each time we mow. Look for a more expansive drainage project this fall on the 4th fairway. Thanks and we'll see you on the course!

February 13, 2013

First tee irrigation project


Last week the crew worked hard to install new irrigation heads around #1 tee.  This area is notorious for being very dry during the summer months and requires daily hand watering.  By installing an additional 8 irrigation heads, the slope heading up to the putting green, as well as the turf surrounding the oak tree will now be sufficiently watered. 

The pictures below help describe the process.

Once the spacing of the irrigation heads had been determined,
the crew began by removing the sod and laying plywood before trenching.
 
With the plywood in place, we trenched all the lines in order to install our 1 1/2" pvc pipe. 

Buzz inspecting the project.


 
With the trench cleaned and measured for a depth of 18", the crew began the process
 of installing the irrigation pipe.  (Notice the huge rock on the bottom left of the picture. 
The crew ran into several big rocks throughout this process
which certainly slowed down this project.)


With the pvc pipe in the ground, the crew started the process of replacing the soil
that had been removed during trenching. 


Carlos carefully replacing the sod.




View from the sidewalk heading down to the golf shop.